J.E. McAmis maintains a modern fleet of ABS classed dredging equipment, barges, tugboats and support vessels.  

Projects

Date: 2009

The Interim Corner Cut-off project was performed for the Canaveral Port Authority by J.E. McAmis, and consisted of approximately 225,000 cubic yards of upland excavation and another 300,000...

Date: 2009

Work entailed raising approximately 450 linear feet of the existing North Jetty to El. +8.0 feet MLLW. Construction included the manufacture and installation of marine mattresses, placement...

Date: 2008

The Port of Anchorage Intermodal Expansion Project consisted of dredging of more than 150,000 cubic yards of soft sediments and stiff clay materials to a depth of -53’ with a tidal range of more than 30’. Upon...

Date: 2007

The Herbert Hoover Dike Project was the first phase of a series of pilot projects for the U.S. Army Corps of Engineers, undertaken to stabilize the dike surrounding Lake Okeechobee. The...